Construction PHASES
Masonry
Our masons start by installing bats and leveling the pool beam. Once the beam has been leveled and prepared they will begin by installing coping to the pool beam. Once the coping is completed, the waterline tile will be installed. In some case cover plates may need to be installed for an automatic pool cover. If your pool requires cover plates, the mason will level the pool beam then return once the cover plates have been installed. Tile and coping must be installed before a any new decking is installed to your project. When a new cantilever deck is being install the pool beam must be leveled before the deck is poured.